On June 30, 2020, the Huaxin Cement aggregate production line EPCO project with capacity of 2000t/h contracted by Shanghai SANME held a commissioning ceremony.
Huaxin Cement 2000t/h aggregate production line EPCO project mainly process waste rock that cannot be used for cement production. The total investment is 230 million, with an annual output of 5 million tons of aggregate and 1 million tons of manufactured sand.
The raw material is mainly dolomite, so SANME specially customized the four-stage crushing and screening process of “jaw crusher + impact crusher + cone crusher + fine sand making building” for this project.
Huaxin Cement 2000t/h aggregate production line EPCO project mainly process waste rock that cannot be used for cement production. The total investment is 230 million, with an annual output of 5 million tons of aggregate and 1 million tons of manufactured sand.
The raw material is mainly dolomite, so SANME specially customized the four-stage crushing and screening process of “jaw crusher + impact crusher + cone crusher + fine sand making building” for this project.